Rick's full report
We're in the final stages of completing the exterior of the Tiny Home, and it should be finished by the end of this week. The progress is visible from the highway.
On the interior, Dominick is currently running the water lines, and we already have the shower, toilet, and sink lines installed, as well as holes cut in the floor for the vent and waste. We're on track to finish this week. Rick has prepared the plumbing plans for inspection and is finalizing the electrical plans, aiming to start the electrical work next week.
For heating, we're using a mini-split heat pump unit from Mitsubishi. We've calculated the necessary BTUs using a manual J program to ensure it's suitable for the home.
This week, we're also planning to finish the interior walls and the loft. We're pushing to stay on schedule to have everything completed by the end of the school semester.
Additionally, starting this Friday, the Beauty and the Beast play dates will begin. Please see the playbill below for times and dates.
CURRENT BUILD
Summit High School ADU
2026-2027 school year
This year's Careers in Construction project is a two-bedroom, one-bath modular ADU being constructed by Summit High School students alongside local trades professionals.
The two modular sections are being built at the high school and will be transported to Summit Cove, where they'll become part of a permanent residence for a local homeowner.
874 SQ. FT.
Total living space
2 BEDROOMS
Plus 1 Bathroom
SPRING 2027
Target Completion
This week in photos
A closer look at the project.

Click a photo to enlarge
Your support helps us continue to give Summit County's kids
real world, hands-on experience and exploration into skilled trades pathways.