Rick's full report
This past week marked the return to school, with the stage set now completed. Art and theater students are diligently adding the finishing touches to paint and decorations.
Progress on the Tiny Home continues to impress. The team laid out the metal trim and began installing the metal board and batten around the base of the home. Additionally, we received pre-stained shiplap cedar siding from Specialty Woods Product, generously donated to the project.
As for the plumbing, the wall has been furred out, as the water lines will not be housed inside the 2 x 4 wall. Dominick is set to begin this week, putting in water lines and collaborating with the students. In terms of electrical work, Team Lead Rick Fout has received clarification on the requirements and should be ready to start laying out the electrical work in the second week of March.
Overall, the Tiny Home project remains on schedule to be completed by the end of the school year.
CURRENT BUILD
Summit High School ADU
2026-2027 school year
This year's Careers in Construction project is a two-bedroom, one-bath modular ADU being constructed by Summit High School students alongside local trades professionals.
The two modular sections are being built at the high school and will be transported to Summit Cove, where they'll become part of a permanent residence for a local homeowner.
874 SQ. FT.
Total living space
2 BEDROOMS
Plus 1 Bathroom
SPRING 2027
Target Completion
This week in photos
A closer look at the project.

Click a photo to enlarge
Your support helps us continue to give Summit County's kids
real world, hands-on experience and exploration into skilled trades pathways.