The modular ADU, taking shape!

SUMMIT HIGH SCHOOL • HANDS-ON LEARNING

Siding & Pocket Doors!

Rick's Field Report 02/05/26

Siding and pocket-door hardware keep the team moving while it awaits drywall delivery.

This week on the build

A few years of building, learning and a little Rick-style commentary.

Find a field report

Siding & Pocket Doors!

February 5, 2026

Siding and pocket-door hardware keep the team moving while it awaits drywall delivery.

Another Wall Goes UP!

January 29, 2026

Siding nears completion, foam insulation begins, and the crew prepares for inspection and drywall.

Siding, Insulation & Another Pass!

January 22, 2026

Siding continues, insulation begins, and the crew celebrates a passed rough electrical inspection.

Unfinished stud wall with window opening-2.png

Share your skills. Support the classroom. Make a difference. 

Help build their next chapter.

© 2023 Summit County Builder's Association

​

699 Summit Blvd, Unit H/PO Box 2245, Frisco, CO 80443

bottom of page